Phase |
Time Period |
Work to be Performed |
Closures / Detours |
1A |
Spring – Fall 2007 |
Construction of islands on McDevitt Street
Drainage work on Forbes Avenue, Boulevard, and Fifth Avenue
Installation of new North Ramp connecting Fifth Ave to Blvd
New sidewalk along Fifth Avenue and Forbes Avenue
No structural work on Boulevard |
Lane closures on Northbound Boulevard West of Bridge
Lane closures on Forbes Avenue from Moultrie Street to McDevitt Place
Lane closures on Fifth Avenue from Craft to the Bath House |
1B |
Summer
2007 |
Drainage work on Forbes Avenue |
Lane restrictions on Forbes Avenue result in 1 through lane of traffic |
2 |
Winter – Fall
2008 |
Demolition of existing North Ramp, Boulevard Bridge and South Ramp
Construction of new South Ramp
Construction of new retaining walls
Construction of new Boulevard Bridge and roadway |
Full detours in effect for Boulevard traffic (See Map Insert)
New North Ramp open for use connecting Fifth Avenue and Boulevard to Downtown
Left lane closures on Forbes from Moultrie Street to Craft Avenue
Forbes Avenue counterflow lane removed and Forbes Avenue open to one-way traffic only |
3 |
Spring 2009 |
Landscaping and Irrigation installation.
Asphalt paving and pavement marking operations |
Daily traffic restrictions during nonpeak hours. |