Boulevard of the Allies Bridge Project (SR885)
Traffic Control / Detours  
Project Home Project History Project Plan / Design Community Meetings Contact Information  
NEW! Click here to submit your questions to us. You can also subscribe to our email list to receive weekly updates!
 
 
Project Plan / Design > Cost Estimates
Overview
Bridge Details
Intersection Details
Aesthetics
Cost Estimates
Project Schedule
Current Contract Information Cost ($)
Mainline Bridge 4.0 M
Retaining Walls 10.5 M
Roadway Costs 13.3 M
Other (lighting, landscaping, etc.) 1.3 M
Total Contract Value $29.1 M

 

Summary of Project Quantities  
Excavation 40,000 cubic yards
Asphalt Paving 22,000 cubic yards
Concrete 13,000 cubic yards
Steel Piling 1,200,000 pounds
Steel Reinforcement 900,000 pounds
Drainage Pipe 4.600 feet
Retaining Walls 3,800 feet
Landscape Plants 8,600 feet

 

 

 